Living Plans · Public assumption audit
Evidence pass 2026-09-28 · open sources only
Public assumption audit · Fortum
Fortum's financial targets, set November 2025
Fortum renewed its targets at Investor Day 2025: comparable RONA of 14%, fleet-availability KPIs, a 1.2 GW ready-to-build pipeline by 2028 and a coal exit by the end of 2027. The first reported year already breaks one: nuclear fleet availability ran at 75% against a >90% target, and 2026 guidance has been cut.
00
Broken
12
Unresolved
00
Holds
- Document
- Fortum's financial targets, set November 2025
- Organisation
- Fortum
- Published
- 2025-11-25
- Audited
- 2026-09-28
- Assumptions
- 12 extracted, 12 checked
- Sources
- 0 public, all dated
Audited from: https://www.fortum.com/investors/why-invest-fortum/financial-targets
§ 01 · How this was made
01
The document, as published
We read only what the organisation published itself, at the address above. Nothing is inferred about its private intentions.
02
Assumptions, in its own words
Each assumption is a belief the plan needs to be true, quoted back to the sentence it came from. Goals and values are not assumptions.
03
Two searches each
One search for what the record says, one aimed at finding the contradiction. The verdict follows the sources, and the sources are listed.
Draft · machine-written, unsigned. No person at Fortum has been asked to sign any verdict here, and none of it is a decision. In the paid product a named human signs or rejects every break, which is what makes the record defensible. This audit is the method shown in public on a document anyone can check.
Nothing in this state.
- Assumption 01Unresolved
Electricity's share of total Nordic energy consumption will grow materially over the coming decades.
- Stated in the document as
- “In the mid- to long-term, electricity is expected to continue to gain a significantly higher share of total energy consumption bringing decades of demand growth for the Nordics.”
- What rests on it
- The entire growth strategy and the EUR 2.5 billion optional capex envelope to 2030.
Evidence trail · 0 sources
No evidence found for or against this assumption. That is not the same as true.
- Assumption 02Unresolved
Fortum's nuclear fleet availability will reach above 90% on a sustained basis.
- Stated in the document as
- “>90% for nuclear”
- What rests on it
- The 8–10 EUR/MWh optimisation premium target for 2026 and the 14% RONA target.
Evidence trail · 0 sources
No evidence found for or against this assumption. That is not the same as true.
- Assumption 03Unresolved
Fortum can sustain a net debt to comparable EBITDA ratio below 2.5 times while executing its investment programme.
- Stated in the document as
- “Leverage guidance: Net debt/comparable EBITDA can be a maximum of 2.5 times (at the end of Q1 2026: 1.1 times).”
- What rests on it
- The BBB credit rating target and the dividend payout ratio of 60–90% of comparable EPS.
Evidence trail · 0 sources
No evidence found for or against this assumption. That is not the same as true.
- Assumption 04Unresolved
Fortum's fixed cost base will remain at approximately EUR 870 million per year from 2026 onwards.
- Stated in the document as
- “Fortum estimates that the new run-rate for its fixed cost base in 2026 will be approximately EUR 870 million, including the fixed cost increase of EUR 20 million in the Swedish property tax from 2025.”
- What rests on it
- The 14% comparable RONA target and the EUR 100 million cost reduction programme outcome.
Evidence trail · 0 sources
No evidence found for or against this assumption. That is not the same as true.
- Assumption 05Unresolved
Industrial decarbonisation investment in the Nordic region will recover after the current period of postponement.
- Stated in the document as
- “As the operating environment shows increased uncertainty, reduced visibility and postponement of industrial investments, the company specified its business portfolio, clarified capital allocation and set new strategic targets with measurable key performance indicators (KPIs).”
- What rests on it
- The optional EUR 2.5 billion additional investment capacity and the 'drive decarbonisation in industries' strategic priority.
Evidence trail · 0 sources
No evidence found for or against this assumption. That is not the same as true.
- Assumption 06Unresolved
Fortum can build a ready-to-build solar and onshore wind pipeline of 1.2 GW by end of 2028.
- Stated in the document as
- “Ready-to-build pipeline for solar and onshore wind: 1.2 GW by end of 2028 (currently ~8 GW in permitting phase)”
- What rests on it
- The growth capex of approximately EUR 750 million and the customer-driven growth options target.
Evidence trail · 0 sources
No evidence found for or against this assumption. That is not the same as true.
- Assumption 07Unresolved
Fortum can achieve a hedged share of rolling 10-year outright generation volume above 25% by end of 2028.
- Stated in the document as
- “Hedged share of rolling 10-year outright generation volume: >25% by end of 2028”
- What rests on it
- The 'stable, scenario-resilient cash flows' commercialisation target and dividend policy sustainability.
Evidence trail · 0 sources
No evidence found for or against this assumption. That is not the same as true.
- Assumption 08Unresolved
Fortum will exit coal entirely by the end of 2027.
- Stated in the document as
- “coal exit by the end of 2027”
- What rests on it
- SBTi-validated net-zero target for 2040 and the decarbonised portfolio narrative used to attract industrial customers.
Evidence trail · 0 sources
No evidence found for or against this assumption. That is not the same as true.
- Assumption 09Unresolved
New ready-to-deploy flexibility capacity of 2.5 GW can be secured by end of 2028, including customer assets requiring no Fortum capital expenditure.
- Stated in the document as
- “New ready-to-deploy flexibility: 2.5 GW by end of 2028”
- What rests on it
- The flexibility and optimisation core business growth and the optimisation premium target.
Evidence trail · 0 sources
No evidence found for or against this assumption. That is not the same as true.
- Assumption 10Unresolved
Fortum's hydro fleet availability will remain above 95% on a sustained basis.
- Stated in the document as
- “>95% for hydro”
- What rests on it
- The optimisation premium target of 8–10 EUR/MWh for 2026 and the 14% RONA target.
Evidence trail · 0 sources
No evidence found for or against this assumption. That is not the same as true.
- Assumption 11Unresolved
New investments in Fortum's chosen technologies will meet a project WACC hurdle of at least 150 basis points above WACC.
- Stated in the document as
- “Hurdle rates for new investments of project WACC +150 bps to +400 bps hurdles depending on technology or investment project, as well as environmental targets.”
- What rests on it
- The 14% comparable RONA target and the optional EUR 2.5 billion additional investment capacity.
Evidence trail · 0 sources
No evidence found for or against this assumption. That is not the same as true.
- Assumption 12Unresolved
Fortum will maintain a credit rating of at least BBB from major rating agencies.
- Stated in the document as
- “Stable credit rating of at least BBB.”
- What rests on it
- Access to capital markets at acceptable cost to fund the EUR 2.0 billion committed capex programme.
Evidence trail · 0 sources
No evidence found for or against this assumption. That is not the same as true.
Nothing in this state.
§ 05 · One ask
Next week's audit, by email, the day it is published.
One document a week, its assumptions, the verdicts and the sources. Nothing else is ever sent to this list.
The uncomfortable version of this page, about your plan.
Send the strategy you already have. The register of the assumptions it rests on comes back free, in your own sentences. The evidence pass is €390, VAT excluded, and every verdict arrives with the dated sources behind it.